15.02.2021

The construction of the Zelenoluzhskaya subway line continues in Minsk. The other day, the first stage has been completed – the tunnel to the future Nemarshansky Garden station was finished. This is the longest tunnel in Minsk subway - 1830 meters long and 6 meters wide. Work has been underway since January last year. The mechanical digging equipment drills about 12 meters day. The next stage of construction, the digging of a parallel tunnel, will begin in May.